Our New Build Process
Our Build Process
This example serves as a general guide for your home construction schedule. With over 30 skilled contractors collaborating to create your exceptional home, we handle all scheduling and quality control to ensure a seamless process.
Foundation
- Begin Excavation of the Foundation
- Pour Concrete Footers
- Pour Foundation Walls
- Apply Waterproofing to Foundation
- Set Steel I-Beams
- Backfill Foundation to Cover French Drains (foundation may sit due to framers’ schedule)
Framing
- Begin Framing First Floor Deck & Walls (pour basement depending upon lot)
- Frame Second Floor & Walls
- Set Roof Trusses
- Install Roof Sheathing
- Finish Framing Interior Walls
- Pour Concrete in Basement & Garage
- Install Windows & Interior Stairs
Mechanical and Insulation
- Rough-In Plumbing, HVAC, Electric, Technology (if in contract)
- Install Shingles on Roof
- Air Seal House & Inspections
- Install Exterior Wall Insulation & Specified Soundproofing
Exterior
- Start Exterior Facade – Brick, Siding, Stone (can vary a few weeks after this)
Interior Finishes
- Board Interior Walls (finalize your flooring & countertops selections)
- Drywall Finish Interior Walls
- Prime Interior Walls Interior Doors & Trimwork
- Install Kitchen Cabinetry & Bath Vanities
- Template for Countertops
- Install Interior Railing
- Paint Trimwork & Doors
- Install Countertops
- Plumbing Finish – Install Faucets & Toilets
- Electric Finish – Install Lighting Fixtures
- HVAC Finish & Install A/C
- Install Hardwood Flooring
- Install Mirrors, Shelving, & Shower Doors
- Rough Grade Lot
- Install Carpet
- Finish Paint Walls
Finishing Touches
- Final Inspections
- Final Clean Home & Final Paint Touch-Ups